Anticipated Project Schedule, Phase III – Rockport Road to Rogers Street


Milestone Target Dates
Initial Public Information Meeting April 15, 2019
Preliminary Design May 2019 – March 2020
Final Public Information Meeting April 2020
Environmental Approval (AI) July 2020
Land Acquisition July 2021 – May 2022
Final Design Complete June 2022
Clearing & Staking of Right-of-Way October 2022
Utility Relocations November 2022 – July 2023
Bid Letting July 12, 2023
Road & Bridge Construction Sept 2023 – June 2025